Avgerage project completion time drops down

    Date:

    Share post:

    • Avgerage time to complete residential projects of 500+ units in top seven cities down to 4.9 years from H1 2014 – H1 2024 compared to 6.1 years in 2010-2019 period
    • Chennai saw highest reduction of 36% in completion time, from 5.6 years in 2019 to 3.6 years in H1 2024; in Bengaluru and Hyderabad, completion time down to 4.8 & 4.2 years respectively
    • NCR saw a significant 25% reduction – from 7.2 years in 2019 to 5.4 years in H1 2024
    • In MMR, average completion time reduced to 5.2 years in H1 2024 from 6.5 years in 2019 – a reduction of 20%
    • In Kolkata, homebuyers’ wait for large projects longest at 5.7 years with a just 10% reduction from 6.3 years in 2019
    • For smaller projects (100-500 units), top 7 cities avg. wait time reduced to 4.0 years in H1 2024 from 4.9 years in 2019
    • Project completion impact on unsold inventory – 13% reduction b/w H1 2019-end to H1 2024-end.

    In what can be seen as a combined effect of RERA, modernisation of construction technology, and the increasing market share of large and listed developers, the last decade has seen homebuyers’ wait for possession in large under-construction projects in the top seven cities reduce to 4.9 years, from 6.1 years in the 2010-2019 period, stated a recent report.

    Commenting on the data, Anuj Puri, Chairman – ANAROCK Group, says, “Latest ANAROCK data reveals that the average time to complete large residential projects of 500+ units in top 7 cities clocked in at 4.9 years from 2014-H1 2024, from 6.1 years in the preceding decade. Large and listed players account for nearly 34% of the market today. The stringent rules imposed on project delays by the regulatory authorities have also been a key factor in reducing the completion time.

    All projects launched and completed between 2010-2019 and 2014-H1 2024 in the top seven cities were analysed in the study, and were further segregated into developments with less than 500 units larger ones with over 500 units.

    When it comes to completing large projects, the top southern cities were markedly ahead of their northern, western, and eastern counterparts. For all large projects launched and completed between 2014 and H1 2024, the average completion time was lowest in Chennai with 3.6 years, while Hyderabad and Bangalore clocked in at 4.2 and 4.8 years respectively.

    “For most large projects in NCR and MMR, developers had purchased land outright, thereby compromising their overall financial health and delivery capability,” says Puri.

    “On the other hand, most projects in the main southern cities are joint developments where landowners usually get a certain share of the developed units. In NCR, extreme weather conditions and the statutory restrictions imposed on construction when the pollution levels rise also play affect construction timelines in the region. Most developers have gradually reduced their leverage and with stronger financial conditions, are able to focus on execution.”

    It is noteworthy that at 36%, Chennai has the highest reduction of construction time among the top 7 cities, despite incessant rains during the monsoon season causing major challenges..

    Small & Large Projects: Completion Trends (2014-H1 2024)

    The average time taken to complete smaller projects of less than 500 units in the top 7 cities was 4.0 years, and 4.9 years for large projects of >500 units each.

    • In Kolkata, large projects launched and completed between 2014 to H1 2024 took the longest average time to complete, at 5.7 years.
    • In MMR, it took an average of 4.7 years to complete small projects, and around 5.2 years for large projects.
    • In Pune, the average project completion time was 4.3 years for small projects, and 5.4 years for large ones.
    • In NCR, homebuyers waited an average of 4.7 years for small projects and 5.4 years for large ones.
    • In Chennai and Hyderabad, the average completion time for small projects was 3 years and 3.1 years respectively, and 3.6 and 4.2 years for large projects, respectively. In Bangalore, it was 3.5 years for small projects and 4.8 years for large ones.
    Source: ANAROCK Research

    As larger projects gain momentum across the cities and new construction technology is implemented, construction time will reduce further. Continuity of execution across major projects is becoming a major factor with financially sound developers whose sales volumes have enabled continued cashflows.

    Related Posts

    Latest posts

    ANAROCK Reports Rise in Home Prices Across Top 7 Cities in H1 FY25

    In H1 FY2024, avg. ticket size of homes sold across top 7 cities was approx. INR 1 Cr Approx....

    Subway Opens 850th Outlet at Elan Miracle Mall

    Subway, the world-renowned quick-service restaurant chain, reached a significant milestone today with the grand opening of its 850th...

    Land Acquisition for ‘New Noida’ Project Begins

    The development of a new city in the National Capital Region (NCR) has taken a significant step forward...

    Equity Investments in Indian Real Estate to Exceed $10bn in 2024

    Equity investments in the Indian real estate sector are poised to exceed $10 billion in 2024, driven by...