As of April 2024, a startling revelation has emerged regarding the state of infrastructure projects in India. as reported by The Economic times According to a report from the Ministry of Statistics and Programme Implementation (MoSPI), a total of 448 infrastructure projects, each requiring an investment of Rs 150 crore or more, have been plagued by cost overruns exceeding Rs 5.55 lakh crore.
Extent of the Issue
MoSPI’s report scrutinizes 1,838 projects in total. Among these, 448 projects have reported cost overruns, while an additional 792 projects have experienced delays. The original cost estimation for these endeavors stood at a substantial Rs 27,64,246.50 crore. However, the anticipated completion cost has ballooned to approximately Rs 33,19,601.84 crore, signifying an overall cost overrun of over Rs 5,55,355.34 crore, equivalent to 20.09% of the original cost.
Financial Snapshot
Up until April 2024, the expenditure incurred on these projects amounted to Rs 1,692,997.5 crore, representing 51% of the anticipated project cost. Despite this significant expenditure, the number of delayed projects decreased to 514 when considering the delay based on the latest schedule of completion.
Time Overruns and Contributing Factors
A detailed analysis of the delayed projects reveals a range of challenges. Among the 792 delayed projects, 220 have faced delays ranging from 1 to 12 months, 192 projects have endured delays of 13 to 24 months, 259 projects have been stalled for 25 to 60 months, and 121 projects have languished for over 60 months. The average time overrun across these projects stands at a substantial 35.4 months.
Root Causes
Key factors contributing to these delays include:
- Land Acquisition: Challenges in acquiring necessary land for project execution.
- Environmental Clearance: Regulatory hurdles and environmental assessments causing project delays.
- Financial Issues: Budgetary constraints or funding shortages impeding project progress.
- Contractual/Internal Issues: Disputes or inefficiencies within project management structures.
- Manpower Shortage: Inadequate workforce availability impacting project timelines.
- Litigation Issues: Legal disputes or judicial proceedings stalling project execution.
Conclusion: Charting a Path Forward
Addressing the challenges posed by cost overruns and delays in infrastructure projects demands a collaborative effort. Government bodies, project stakeholders, and regulatory authorities must work together to streamline processes, enhance project oversight, and implement proactive measures to mitigate potential risks.
By fostering transparency, accountability, and effective communication, we can navigate the complexities of infrastructure development, ensuring timely project delivery and optimizing resource utilization for sustainable growth and socio-economic advancement.